You will no longer be able to turn left onto 5th from westbound L St. To facilitate traffic flow, cars will turn right and travel north on 5th.
• 7-4, 7:00a-1:30p. Street closed: 8th between Market & Island for Farmer's Market.
• 7-4, 8:00a-2:30p. Street closed: Date between Kettner and Union for Farmer's Market.
• 7-5, 8:00a-2:00p. Streets closed: Third between Market and J St and J St between Third & Fourth for Farmer's Market.
• 7-11, 7:00a-1:30p. Street closed: 8th between Market & Island for Farmer's Market.
• 7-11, 8:00a-2:30p. Street closed: Date between Kettner and Union for Farmer's Market.
• 7-12, 8:00a-2:00p. Streets closed: Third between Market and J St and J St between Third & Fourth for Farmer's Market.
• 7-18, 7:00a-1:30p. Street closed: 8th between Market & Island for Farmer's Market.
• 7-18, 8:00a-2:30p. Street closed: Date between Kettner and Union for Farmer's Market.
• 7-18, 9:15a-2:30p. University Avenue (Hillcrest) to 6th Avenue and Upas/Balboa Drive for the LGBT Run and Stride with Pride and the LGBT Parade.
• 7-18, 10:00a-11:59p. Street closed: J St between 6th to 10th for tailgate party.
• 7-18 & 7-19, noon-10:00p. Heavy pedestrian traffic: Balboa Park (west side of park at Marston Point along Laurel Street between 6th Ave. & Balboa Dr for the San Diego LGBT Pride Festival.
• 7-19, 7:00-11:00a. Streets/sidewalks closed: From Embarcadero Marina Park North parking lot, north on Kettner Blvd, west on Harbor Dr, north on Pacific Hwy, west on Grape, south on the Embarcadero Esplanade back to Embarcadero Marina Park North for San Diego Blood Bank 5K Walk/Run.
• 7-19, 8:00a-2:00p. Streets closed: Third between Market and J St and J St between Third & Fourth for Farmer's Market.
• 7-19, 10:30a-3:30p. Streets closed: State between A St & Ash AND India between A St & Ash for Little Italy Stickball Summer League Competition.
• 7-22, 6:00-9:00p. Heavy pedestrian and traffic on Harbor Drive near the Convention Center for Comic-Con Preview Night.
• 7-23 thru 7-28, all day and most of the night. Heavy pedestrian and traffic due to Comic-Con Convention. Watch out for the unusually dressed attendees!
• 7-25, 7:00a-1:30p. Street closed: 8th between Market & Island for Farmer's Market.
• 7-25, 8:00a-2:30p. Street closed: Date between Kettner and Union for Farmer's Market.
• 7-26, 8:00a-2:00p. Streets closed: Third between Market and J St and J St between Third & Fourth for Farmer's Market.
• 7-26, 10:30a-3:30p. Streets closed: State between Elm & Fir AND Union between Cedar & Date for Little Italy Stickball Summer League Competition.
• Now thru Winter 2010, one southbound lane of Harbor Dr south of Convention Center Way.
• Now thru Winter 2010, one northbound left-turn lane on Harbor Dr at Convention Center Way.
Sewer & water mains are being replaced in the Little Italy neighborhood. The anticipated project completion is December 2009.
Areas affected during the month of June/July/August:
• Now thru 7-21, 8:30a-3:30p. State from West Date to West Grape.
• 7-13 thru 8-6, 9:30a-5:30p. Front from A St to Beech.
• 7-31 thru 8-25, 9:30a-5:30p. Front from Beech to Date.
Water main lines are being replaced within the Little Italy, Columbia, and Marina Neighborhoods.
The entire work is located within developed streets and will be constructed using open trench method. This project involves realignment of approximately 10,162 lineal feet (LF) of water main. The new mains will be parallel to the existing mains in the same street. The existing 16” cast iron mains will be abandoned after the acceptance of the new mains. The majority of the water mains are 16-inch in diameter. The project will replace a small footage of 6-inch and 12-inch.
Streets impacted by Water Group 532 are: North Harbor Dr (beginning at Laurel, south to the intersection of Pacific Hwy and Harbor Dr) and Pacific Hwy (from Seaport Village to F St).
Streets impacted by Water Group 533 are: North Harbor Dr (beginning west of Harbor Island Dr to the bridge and starting east of Harbor Island Dr to Laurel). This is in the vicinity of the San Diego Airport.
Construction began May 26, 2009 and will be completed by April 12, 2010. Hours: Monday thru Friday 8:30a-3:30p AND Monday thru Friday 9:00p-6:00a.
All work south of Ash will be completed by the end of September 2009.Construction began May 26, 2009 and will be completed by April 12, 2010. Hours: Monday thru Friday 8:30a-3:30p AND Monday thru Friday 9:00p-6:00a.
All work south of Ash will be completed by the end of September 2009.
An event will occur on the following dates and times in July:

Expect traffic congestion on these streets prior to each game:
Pacific Hwy, Hawthorn, Cedar, Ash, Front, 6th, 10th, F St, J St, Imperial
Expect traffic congestion on these streets after each game:
Pacific Hwy, Grape, Elm, A St, E St, G St, 1st, 3rd, 5th, 8th, 11th, 13th, 17th, Imperial
Streets closed 1-hour following each game.
• 6-28 thru 7-1, Association of Women’s Health Obstetric & Neonatal Nurses, 2,500
• 7-1 thru 7-6, National Education Association Annual, 16,500
• 7-3 thru 7-4, Eritrean Sport Federation Awards Reception, 2,500
• 7-11 thru 7-17, Environmental Systems Research Institute, 12,000
• 7-19, Bridal Bazaar, 6,500
• 7-23 thru 7-26, San Diego Comic Con, 126,000
• 7-31 thru 8-2, Home Design & Remodeling Show – Green San Diego Expo, 10,000